Independent Cost Estimate
Plain-English definition
FAR 15.404-1(c) directs the contracting officer, when evaluating proposals, to consider an independent government estimate (IGE) or an independent cost estimate developed by a cost analysis organization independent of the program office. The ICE tests whether proposed costs are realistic and consistent with historical data, technical assumptions, and the statement of work. On major systems, DoD policy often requires ICE teams that do not report to the program manager to avoid optimistic bias. ICE products support negotiation objectives, should-cost reviews, and budget submissions. Contractors rarely see the ICE itself but encounter its effects in fact-finding, requests for certified cost or pricing data, and challenging realism of labor hours or material quantities. When no ICE exists, the contracting officer must still document how price reasonableness was determined under FAR 15.404-1.
Why it matters
A government ICE that is far below your proposal signals tough negotiations or a realism challenge before award.
Where you'll encounter it
Source selection plans, negotiation memoranda, independent cost organizations, and pre-negotiation fact-finding.
Example
After proposal submission, the CO cites an ICE that is 18 percent lower than the offeror's cost volume and requests a bottom-up reconciliation of engineering hours.