Stop Work Order
Plain-English definition
Under the clause at FAR 52.242-15, the contracting officer may by written order, specifically identified as a stop-work order, require the contractor to stop all or part of the work for 90 days after delivery of the order, and for any longer period the parties agree to. The contractor must comply immediately and take all reasonable steps to minimize costs allocable to the stopped work. Within the 90 days, or any agreed extension, the contracting officer must either cancel the order or terminate the covered work under the default or convenience termination clause. If the order is cancelled or expires, the contractor resumes work and may receive an equitable adjustment in delivery schedule or price when the stoppage increased time or cost, provided it asserts the right to adjustment within 30 days after the stoppage ends. The contracting officer may accept a later claim before final payment if the facts justify it. The clause's Alternate I adapts the wording for cost-reimbursement contracts. Contractors should track stoppage costs separately from the first day, because recovery depends on showing what the order caused.
Why it matters
Costs and schedule effects are recoverable only if the contractor tracks them and asserts the adjustment on time.
Where you'll encounter it
Contracting officer letters, contract modifications, FAR 52.242-15 clause text, and termination settlement proposals.
Example
After receiving a stop-work order, the program manager opens a separate charge code to capture standby labor.