- Award ID
- N6247819F4209
- Contractor
- INSIGHT PACIFIC, LLC
- Sub-agency / office
- Department of the Navy
- Award amount
- $10,564,700
- Period of performance
- Aug 22, 2019 – Oct 3, 2024
- NAICS
- 236220 — Commercial and Institutional Building Construction
- PSC
- PSC Z1ED
- Place of performance
- JBPHH, HI, 968535148, USA
- Competition
- FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES · 4 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $10,633,839 · Obligated $10,633,839 · Potential value $10,633,839 · Latest action obligation $69,139
- Parent award
- N6247818D4026
FY18 ST16-2121 DRYDOCK 4 MAIN PUMP 3&4 OVERHAUL, PEARL HARBOR NAVAL SHIPYARD (PHNSY)&INTERMEDIATE MAINTENANCE FACILITY (IMF), JOINT BASE PEARL HARBOR HICKAM (JBPHH), HAWAII
Most recent · Modification P00005 · Jun 16, 2026 · $69,139 action obligation · P00005 PC 16 THIS MODIFICATION IS FOR THE INVESTIGATION, TROUBLESHOOTING, TESTING AND STANDBY TIME FOR THE POWER FAILURE. · N6247819F4209
Modification P00004 · Aug 26, 2025 · $1,090,655 action obligation · WR152308-WON1558421-FY18 ST16-2121 DRYDOCK 4 (DD4) MOD P00004 PC 9 12, JBPHH HI · N6247819F4209
Modification P00003 · Apr 25, 2024 · $594,568 action obligation · WR152308-WON1558421-FY18 ST16-2121 DRYDOCK 4 (DD4) - MOD P00003 - PC 15 · N6247819F4209
Modification P00002 · Feb 29, 2024 · $231,778 action obligation · WR152308-WON1558421-FY18 ST16-2121 DRYDOCK 4 (DD4)- MOD P00002 - PCS 1, 3, 4, 5, 7 · N6247819F4209
Modification P00001 · Feb 15, 2024 · $70,079 action obligation · WR152308-WON1558421-FY18 ST16-2121 DRYDOCK 4 (DD4) MAIN PUMP NO. 3 & 4 OVERHAUL - MOD: P00001-PCM 11 · N6247819F4209
Modification A00004 · May 7, 2021 · $0 action obligation · NO COST TIME EXTENSION · N6247819F4209
Modification A00003 · Aug 6, 2020 · $0 action obligation · WR152308-WON1558421-FY18 ST16-2121 DRYDOCK 4 MAIN PUMP 3&4- THIS MODIFICATION IS TO LIFT THE SUSPENSION OF WORK ISSUED BY TO MOD A00002 DTD 22 MAY 2020. · N6247819F4209
Modification A00002 · May 22, 2020 · $0 action obligation · MOD IS TO EXTEND THE SUSPENSION OF WORK FROM 5/22/2020 TO 7/22/2020 · N6247819F4209
Modification A00001 · Dec 4, 2019 · $0 action obligation · WR152308-WON1558421-FY18 ST16-2121 DRYDOCK 4 MAIN PUMP 3&4-THIS MODIFICATION IS ISSUED TO SUSPEND THE PROJECT FROM 04 DECEMBER 2019 TO 15 MAY 2020, A TOTAL OF 163 CALENDAR DAYS, DUE TO DRYDOCK SCHEDULE CONFLICT. · N6247819F4209
Modification 0 · Aug 22, 2019 · $8,577,620 action obligation · FY18 ST16-2121 DRYDOCK 4 MAIN PUMP 3&4 OVERHAUL, PEARL HARBOR NAVAL SHIPYARD (PHNSY)&INTERMEDIATE MAINTENANCE FACILITY (IMF), JOINT BASE PEARL HARBOR HICKAM (JBPHH), HAWAII · N6247819F4209