- Award ID
- W9123620C2025
- Contractor
- BALFOUR BEATTY CONSTRUCTION, LLC
- Sub-agency / office
- Department of the Army
- Award amount
- $143,902,304
- Period of performance
- Oct 13, 2020 – Jan 22, 2025
- NAICS
- 236220 — Commercial and Institutional Building Construction
- Place of performance
- FORT EUSTIS, VA, 236041400, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 5 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $149,990,300 · Obligated $149,990,300 · Potential value $149,990,300 · Latest action obligation $30,294 · Outlays $-6,632,197
Most recent · Modification A00112 · Jul 1, 2026 · $30,294 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPS BUILDING AND HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE VARIOUS MECHANICAL REVISIONS TO DUCTWORK ROUTING, COOLING TOWERS AND WATER PIPING. · W9123620C2025
Modification A00111 · Jun 28, 2026 · $49,997 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPS BUILDING AND HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO DELETE THE HIGH-EXPANSION FOAM SYSTEM AND PROVIDE ADJUSTMENTS TO THE HANGAR FIRE SUPPRESSION SYSTEM. · W9123620C2025
Modification A00110 · Jun 26, 2026 · $48,000 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE A NEW ROOF ACCESS LADDER WITH ENHANCED SAFETY MEASURES AND TO PROVIDE PROTECTION THROUGH THE RATED ROOF ASSEMBLY. · W9123620C2025
Modification A00109 · Jun 5, 2026 · $13,709 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO ADD DROPPED CEILING AND REVISE SPRINKLERS AND LIGHTING AT THE FIRING RANGE QUEUING AREA. · W9123620C2025
Modification A00108 · May 21, 2026 · $27,206 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 3, FIELD MODIFICATION TO REVISE BREAKERS IN ASSOCIATED PANEL FOR HRC-1 AND TO PROVIDE A SEQUENCE OF OPERATION FOR THE HANGAR DESTRATIFICATION FANS. · W9123620C2025
Modification A00107 · May 13, 2026 · $203,577 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 3, FIELD MODIFICATION TO REVISE NATURAL GAS STUB UPS AT GENERATORS, ADD GYPBOARD TO ASP-3 CEILINGS, RECONFIGURE HVAC DUCT, REVISE TELECOMMUNICATION IN COOP, ADD DUCT SMOKE DETECTORS, AND ADD SIDEWALK. · W9123620C2025
Modification A00106 · Apr 14, 2026 · $220,000 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 3, FIELD MODIFICATION TO PROVIDE UPGRADES TO THE NATURAL GAS SYSTEM AND TO PROVIDE AN ADDITIONAL FUME EXTRACTOR ARM. · W9123620C2025
Modification P00022 · Apr 2, 2026 · $1,212,000 action obligation · CONSTRUCT BATTALION COMPLEX PHASE 2 AND 3 · W9123620C2025
Modification A00105 · Mar 19, 2026 · $61,750 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE GROUNDING FOR THE COOP SHIELDING, ELECTRICAL REVISIONS IN AREA A, A REVISED ROLL-UP DOOR AT THE AID STATION, AND REVISED TELECOMMUNICATIONS OUTLET BOXES. · W9123620C2025
Modification A00104 · Mar 17, 2026 · $66,389 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE CONDENSATE PUMPS FOR THE DOAS UNITS IN PHASE 2 AND TO PROVIDE ELECTRICAL RECEPTACLES FOR THE FIRING RANGE TARGETING SYSTEM. · W9123620C2025
Modification A00103 · Mar 5, 2026 · $87,700 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE CONDENSATE PUMPS FOR THE DOAS UNITS IN PHASE 2 AND TO PROVIDE ELECTRICAL RECEPTACLES FOR THE FIRING RANGE TARGETING SYSTEM. · W9123620C2025
Modification A00102 · Feb 26, 2026 · $158,529 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE ADDITIONAL EMI/RF SHIELDING FOR THE COOP CALL CENTER. · W9123620C2025
Modification A00101 · Dec 4, 2025 · $39,000 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE REVISIONS TO PARTITION WALLS IN THE OPERATIONS BUILDING. · W9123620C2025
Modification A00100 · Nov 20, 2025 · $26,819 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE MISSING ROOF DECK EDGE MATERIAL, CIRCUIT BREAKERS, HANDRAILING, AND A MISSING CANOPY LIGHT · W9123620C2025
Modification A00099 · Oct 24, 2025 · $120,898 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE REVISIONS THE CAA OUTLETS, CABLE TRAY REDISTRIBUTION, AND EXTERIOR FLASHING DETAILS. · W9123620C2025
Modification A00098 · Sep 29, 2025 · $14,407 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE AN EMERGENCY EXIT SIGN AND RELOCATE MASS NOTIFICATION SPEAKERS IN LOG WAREHOUSE. · W9123620C2025
Modification A00097 · Sep 25, 2025 · $112,500 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE REVISIONS TO THE CLOUD CEILINGS IN THE LOBBY AND TEAM ROOM. · W9123620C2025
Modification A00096 · Sep 18, 2025 · $0 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO ADD 10 CALENDAR DAYS TO THE CONTRACT DUE TO ADVERSE WEATHER INCURRED JAN 2021 THROUGH MAY 2025 · W9123620C2025
Modification P00021 · Sep 11, 2025 · $4,155,641 action obligation · W9123620C2025 P00021 - BATTALION COMPLEX PHASE 2 AND 3 - RESOLVE FAA AND PILE CAP DELAY FOR MANGANARO, HEAT EXCHANGER, AND TEMPORARY HEAT WINTERIZATION REA AND RE-ESTABLISH THE CONTRACT COMPLETION DATE. · W9123620C2025
Modification P00020 · Sep 8, 2025 · $661,495 action obligation · W9123620C2025 P00020 CONSTRUCTION OF BATTALION COMPLEX - M0112 STORMWATER REALIGNMENT, M0187 PH3 DECK ANGLE STEEL, M0185 LAUNDRY ROOM DRAIN, M0156 P-8 THRU P-16 SOO, M0006-3E DOMINION PILE, M0008-2E DOMINION FAA, M0188 WILLIAMSON AND WILMER REA. · W9123620C2025
Modification A00095 · Aug 19, 2025 · $197,071 action obligation · CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION DIRECTING THE CONTRACTOR TO PROCEED REDESIGNED SHIELDING IN THE COOP · W9123620C2025
Modification P00019 · Aug 4, 2025 · $0 action obligation · P00019 IS HEREBY MODIFIED TO IMPLEMENT CLASS DEVIATION 2025-O0003 AND CLASS DEVIATION O0004. · W9123620C2025
Modification A00094 · Jul 23, 2025 · $59,400 action obligation · FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION, M0170-2/A00094 IS TO PROVIDE AN NTP FOR PREPARATION WORK AND MATERIAL PURCHASE FOR LONG LEAD ITEMS. · W9123620C2025
Modification A00093 · Jul 9, 2025 · $24,499 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FIELD MODIFICATION TO REVISE THE SEQUENCE OF OPERATIONS FOR EXHAUST FANS AND REVISE LOUVER CONFLICTS FOR THE HVAC SYSTEM · W9123620C2025
Modification A00092 · Jul 9, 2025 · $30,389 action obligation · FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO ADD FIRE PROTECTION TO GYM STEEL COLUMN, REVISE THERAPY TUB SERVICE LINES, AND ADD A HEATER TO ROOM 1300. · W9123620C2025