- Award ID
- W9123623C2022
- Contractor
- MANHATTAN CONSTRUCTION COMPANY LLC
- Sub-agency / office
- Department of the Army
- Award amount
- $111,991,428
- Period of performance
- May 1, 2023 – Oct 14, 2026
- NAICS
- 236220 — Commercial and Institutional Building Construction
- Place of performance
- FORT MYER, VA, 222119500, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 5 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $115,173,270 · Obligated $115,172,270 · Potential value $115,260,170 · Latest action obligation $72,129 · Outlays $4,293,771
Most recent · Modification A00022 · Jun 29, 2026 · $72,129 action obligation · SE034 TITLE: JOINTS BETWEEN COLUMNS - RFI-0327 SE038 TITLE: BLDG E - STUB COLUMNS - RFI-0429SE080 TITLE: BLDG E - SHEAR AND RW - RFI-0418SE081 TITLE: BLDG E - RW CONTROL JT DETAIL - RFI-0467SE086 TITLE: WEST PARCEL TUNNEL WALL - RFI-0498 · W9123623C2022
Modification P00017 · Jun 24, 2026 · $150,000 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II - OPERATIONS COMPLEX, ARLINGTON, VA · W9123623C2022
Modification A00021 · Jun 18, 2026 · $200,161 action obligation · SE013 - BOLLARD REVISIONS - RFI-0164 · W9123623C2022
Modification A00020 · Jun 3, 2026 · $228,773 action obligation · SE084 - ARLINGTON COUNTY WATER METER FEE · W9123623C2022
Modification A00019 · May 21, 2026 · $17,937 action obligation · SE039 - PEDESTAL BLUE LIGHT - RFIS 0403 AND 422 · W9123623C2022
Modification P00016 · Apr 1, 2026 · $1,572,473 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II - OPERATIONS COMPLEX, ARLINGTON, VA · W9123623C2022
Modification A00018 · Mar 20, 2026 · $72,150 action obligation · TIA - SUBCONTRACTOR COSTS · W9123623C2022
Modification PZ0015 · Feb 5, 2026 · $245,227 action obligation · TIA - SUBCONTRACTOR COSTS · W9123623C2022
Modification A00017 · Jan 21, 2026 · $238,230 action obligation · CHANGE: SE002 TITLE: CONTROLLED RECEPTACLES · W9123623C2022
Modification P00014 · Dec 18, 2025 · $18,064 action obligation · A. SCOPE OF WORK CHANGE: SE019 TITLE: BLDG B - UNSUITABLE SOILS AT FOUNDATIONSPROVIDE LABOR, EQUIPMENT, AND MATERIAL TO EXCAVATE, DISPOSE AND REPLACE UNSUITABLE SOILS ENCOUNTERED BELOW THE BUILDING B FOOTINGS. REMOVE UNSUITABLE SOILS AND REPLACE · W9123623C2022
Modification A00016 · Nov 25, 2025 · $83,315 action obligation · A. SCOPE OF WORK CHANGE: SE019 TITLE: BLDG B - UNSUITABLE SOILS AT FOUNDATIONSPROVIDE LABOR, EQUIPMENT, AND MATERIAL TO EXCAVATE, DISPOSE AND REPLACE UNSUITABLE SOILS ENCOUNTERED BELOW THE BUILDING B FOOTINGS. REMOVE UNSUITABLE SOILS AND REPLACE · W9123623C2022
Modification P00013 · Aug 27, 2025 · $300,000 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II - OPERATIONS COMPLEX, WEST PARCEL BOUNDARY WALL PART 2 NTE · W9123623C2022
Modification A00015 · Aug 6, 2025 · $131,889 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATION COMPLEX, MODIFICATION # PROVIDES ALL LABOR AND MATERIALS NECESSARY TO PERFORM SE019, BLDG. B UNSUITABLE SOILS AT FOUNDATIONS · W9123623C2022
Modification A00014 · Jul 31, 2025 · $41,709 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATION COMPLEX, MODIFICATION A00014 PROVIDES ALL LABOR AND MATERIALS NECESSARY TO PERFORM SE042 - WP TESTING & REMOVAL OF POSSIBLE ASBESTOS LINE, AND SE049 - WP ESTABLISHMENT OF TURF. · W9123623C2022
Modification A00013 · Jul 24, 2025 · $63,240 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATION COMPLEX, MODIFICATION # PROVIDES ALL LABOR AND MATERIALS NECESSARY TO PERFORM A00013 (SE026, BLDG. D INTAKE & EXHAUST SEPARATION AND SE028, LOCK CYLINDER REVISION). · W9123623C2022
Modification A00012 · Jul 10, 2025 · $198,996 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATIONS COMPLEX, MODIFICATION A00012 PROVIDES ALL LABOR AND MATERIAL NECESSARY TO PERFORM CHANGE ORDERS SE016, SE021, SE041, SE048. · W9123623C2022
Modification P00012 · Jun 25, 2025 · $200,000 action obligation · ANCSE PH II OPERATIONS COMPLEX, ARLINGTON, VIRGINIA WEST PARCEL BOUNDARY WALL · W9123623C2022
Modification P00011 · Jun 18, 2025 · $0 action obligation · OPERATIONS COMPLEX · W9123623C2022
Modification P00010 · Jun 17, 2025 · $401,998 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATIONS COMPLEX. SETTLEMENT FOR CONTRACTOR TIA DELAY COSTS DUE TO DIFFERING SITE CONDITIONS. · W9123623C2022
Modification A00011 · May 14, 2025 · $10,974 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATION COMPLEX, MODIFICATION # PROVIDES ALL LABOR AND MATERIALS NECESSARY TO PERFORM CHANGE ORDERS SE032, SE036, AND SE037 · W9123623C2022
Modification P00009 · Mar 18, 2025 · $145,265 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATIONS COMPLEX. ON-SITE CONSTRUCTION TEMPORARY TRAILER REVISIONS FROM ONE EACH 4,4040 SF OFFICE MODULAR TRAILER TO THREE EACH 24' X 60' OFFICE MODULAR TRAILERS. · W9123623C2022
Modification A00010 · Feb 25, 2025 · $31,335 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATION COMPLEX, MODIFICATION A00010 PROVIDES ALL LABOR AND MATERIALS NECESSARY TO PERFORM SE010, ELEVATOR HOISTWAY SIZE - RFI-0105 · W9123623C2022
Modification A00009 · Jan 2, 2025 · $55,133 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATIONS COMPLEX, MODIFICATION A00009 PROVIDES ALL LABOR AND MATERIALS TO PERFORM SE007 (MISCELLANEOUS DIFFERING SITE CONDITIONS), 030 (METER VAULT M2 CONFLICT), 031 (RELOCATE HH-OPS-06). · W9123623C2022
Modification A00008 · Nov 20, 2024 · $91,115 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATION COMPLEX, MODIFICATION A00008 PROVIDES ALL LABOR AND MATERIALS NECESSARY TO PERFORM SE025, FRENCH DRAIN BEHIND BUILDING B · W9123623C2022
Modification A00007 · Nov 12, 2024 · $12,117 action obligation · ARLINGTON NATIONAL CEMETERY SOUTHERN EXPANSION PHASE II OPERATION COMPLEX, MODIFICATION A00007 PROVIDES ALL LABOR AND MATERIALS NECESSARY TO PERFORM SE0029, REMOVAL OF EXISTING VDB · W9123623C2022