- Award ID
- W9127S24C0001
- Contractor
- MCCORMICK INDUSTRIAL ABATEMENT SERVICES, INC.
- Sub-agency / office
- Department of the Army
- Funding agency
- Corps of Engineers - Civil Works
- Award amount
- $14,112,238
- Period of performance
- Dec 19, 2023 – Oct 8, 2028
- NAICS
- 237990 — Other Heavy and Civil Engineering Construction
- Place of performance
- RUSSELLVILLE, AR, 728028462, USA
- Competition
- FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES · Set-aside: SMALL BUSINESS SET ASIDE - TOTAL · 3 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $15,089,645 · Obligated $15,089,645 · Potential value $17,374,864 · Latest action obligation $103,009 · Outlays $489,653
TAINTER GATE PAINTING AND REHABILITATION AT ARTHUR V. ORMOND LOCK AND DAM. INITIAL DURATION 1,455 DAYS AFTER RECEIPT OF NTP. TOTAL DURATION 1,815 IF ALL OPTIONS EXERCISED.
Most recent · Modification A00007 · Jul 6, 2026 · $103,009 action obligation · W9127S24C0001 ORMOND TAINTER GATE PAINTING A00006 QTY INCREASECONTRACT AMOUNT INCREASED BY $103,009.00REVISED CONTRACT COMPLETION DATE: 22 MAY 2029 · W9127S24C0001
Modification A00006 · Apr 10, 2026 · $141,552 action obligation · W9127S24C0001 ORMOND TAINTER GATE PAINTING A00005 MISC FLANGE REPAIR/QTY INCREASECONTRACT AMOUNT INCREASED BY $141,552.00REVISED CONTRACT COMPLETION DATE: 8 JANUARY 2028 · W9127S24C0001
Modification A00005 · Feb 3, 2026 · $232,951 action obligation · CONTRACT W9127S24C0001, TAINTER GATE REHABILITATION, ARTHUR V. ORMOND DAM, ARKANSAS CLIN 0007 WILL NEED TO BE INCREASED BY 140 UNITS.CLIN 0009 WILL NEED TO BE INCREASED 41 UNITS.CLIN 0011 WILL NEED TO BE INCREASED BY 1 UNIT. · W9127S24C0001
Modification A00004 · Jan 7, 2026 · $0 action obligation · CONTRACT W9127S24C0001, TAINTER GATE REHABILITATION, ARTHUR V. ORMOND DAM, ARKANSAS CLIN 0007 WILL NEED TO BE INCREASED BY 140 UNITS.CLIN 0009 WILL NEED TO BE INCREASED 41.522988 UNITS.CLIN 0011 WILL NEED TO BE INCREASED BY 1 UNIT. · W9127S24C0001
Modification A00003 · Sep 24, 2025 · $0 action obligation · CONTRACT NO. W9127S24C0001 FY24 ORMOND TAINTER GATE PAINTING REFERENCE NO. R00006 CHANGE: 00003 TITLE: REA TIME EXTENSION HIGH WATER · W9127S24C0001
Modification A00002 · Aug 28, 2025 · $90,271 action obligation · CONTRACT NO. W9127S24C0001 FY24 ORMOND TAINTER GATE PAINTING REFERENCE NO. R00005- 00006 INCREASE CLIN FOR QTY & DEMOB · W9127S24C0001
Modification P00004 · May 13, 2025 · $0 action obligation · CLAUSE UPDATES IAW CLASS DEVIATIONS 2025-O0003 - RESTORING MERIT BASED OPPORTUNITY IN FEDERAL CONTRACTS (EFFECTIVE 04 MARCH 2025) AND 2025-O0004 - REVOCATION OF EXECUTIVE ORDER ON SUSTAINABILITY (EFFECTIVE 07 MARCH 2025). · W9127S24C0001
Modification A00001 · Apr 14, 2025 · $61,554 action obligation · CONTRACT FOR FY24 ORMOND TAINTER GATE PAINTING REFERENCE NO. R00004 00005 ADD QUANTITIES CLIN 0007 & 0009 · W9127S24C0001
Modification P00003 · Mar 5, 2025 · $5,968 action obligation · TAINTER GATE REHABILITATION AT ORMOND L&D. THIS MOD ADJUSTED QUANTITIES AMONGST CLINS 0007 - 0010, ADDED GIRDER STIFFENER PLATE REPAIR WORK, AND ADDED 20 DAYS TO THE CONTRACT DURATION. · W9127S24C0001
Modification P00002 · Aug 15, 2024 · $2,285,219 action obligation · REHABILITATE TAINTER GATES ON ORMOND LOCK AND DAM, MKARNS. THIS MODIFICATION EXERCISES OPTIONAL CLIN 0013 TO REHABILITATE AN ADDITIONAL 2 GATES. 180 CALENDAR DAYS ARE BEING ADDED TO THE CONTRACT DURATION. · W9127S24C0001
Modification P00001 · May 24, 2024 · $0 action obligation · REHABILITATE TAINTER GATES, ARTHUR V. ORMOND LOCK AND DAM. P00001 REDISTRIBUTES FUNDS FROM EXERCISED OPTION CLIN 0012 TO THE RESPECTIVE CLINS THAT HAVE BEEN INCREASED (0003 THRU 0010). ALSO UPDATES CONTRACT COMPLETION DATE TO MATCH NTP, 22 MAR 2028. · W9127S24C0001
Modification 0 · Dec 12, 2023 · $11,669,225 action obligation · TAINTER GATE PAINTING AND REHABILITATION AT ARTHUR V. ORMOND LOCK AND DAM. INITIAL DURATION 1,455 DAYS AFTER RECEIPT OF NTP. TOTAL DURATION 1,815 IF ALL OPTIONS EXERCISED. · W9127S24C0001