- Award ID
- W912DR23C0017
- Contractor
- CONSIGLI CONSTRUCTION CO., INC.
- Sub-agency / office
- Department of the Army
- Award amount
- $85,866,319
- Period of performance
- May 31, 2023 – Sep 11, 2025
- NAICS
- 236220 — Commercial and Institutional Building Construction
- PSC
- PSC Y1FC
- Place of performance
- MILFORD, MA, 017571663, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 5 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $87,720,369 · Obligated $87,720,369 · Potential value $87,720,369 · Latest action obligation $206,453 · Outlays $15,498,976
Most recent · Modification A00022 · Jun 11, 2026 · $206,453 action obligation · MULTIPLE CHANGES · W912DR23C0017
Modification A00021 · Mar 23, 2026 · $337,186 action obligation · A. SCOPE OF WORK CHANGE AR: CHANGE TO MASONRY CAVITY (RFI-164)CHANGE BI: CORDED WINDOW BLINDS DISCONTINUEDCHANGE BK: EXPOSED COLUMN AT CORRIDOR (RFI-0233)CHANGE BL: EXISTING CRACKED TERRACOTTA STORM DRAINCHANGE BO: DESIGN REVIEW REPORT-ASI#03 · W912DR23C0017
Modification A00020 · Feb 11, 2026 · $336,141 action obligation · A. SCOPE OF WORK CHANGE AR: CHANGE TO MASONRY CAVITY (RFI-164)CHANGE BI: CORDED WINDOW BLINDS DISCONTINUEDCHANGE BK: EXPOSED COLUMN AT CORRIDOR (RFI-0233)CHANGE BL: EXISTING CRACKED TERRACOTTA STORM DRAINCHANGE BO: DESIGN REVIEW REPORT-ASI#03 · W912DR23C0017
Modification A00019 · Nov 12, 2025 · $35,636 action obligation · UNFORESEEN PIPE IN STORM POND (RFI 196) CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00019 · W912DR23C0017
Modification A00018 · Oct 23, 2025 · $17,786 action obligation · BGE ACCESS RD ADD CONCRETE/REINFORCEMENT CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00018 · W912DR23C0017
Modification A00017 · Sep 15, 2025 · $41,118 action obligation · TIA #02 EAST BARRACKS SOFT SOILS CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00017 · W912DR23C0017
Modification A00016 · Sep 9, 2025 · $48,322 action obligation · TELECOM OUTLET REVISIONS (RFI 334/341) CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00016 · W912DR23C0017
Modification A00015 · Sep 2, 2025 · $57,880 action obligation · CHANGES AY AZ CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00015 · W912DR23C0017
Modification A00014 · Aug 12, 2025 · $165,257 action obligation · CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00014 · W912DR23C0017
Modification A00013 · May 30, 2025 · $244,510 action obligation · PANEL WALL ABUTTING CONNECTION CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00013 · W912DR23C0017
Modification A00012 · Apr 22, 2025 · $0 action obligation · WEATHER TIME EXTENSION -JANUARY 2025 CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00012 · W912DR23C0017
Modification A00011 · Apr 11, 2025 · $338,579 action obligation · CHANGE TO BRICK 1 AND BRICK 2 COLORS CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00011 · W912DR23C0017
Modification A00010 · Apr 9, 2025 · $374,647 action obligation · ADD TEMPORARY BYPASS FOR SEWER REMOVAL CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00010 · W912DR23C0017
Modification A00009 · Mar 18, 2025 · $0 action obligation · WEATHER TIME EXTENSION -SEPT 24 & DEC 24 CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00009 · W912DR23C0017
Modification A00008 · Mar 5, 2025 · $283,298 action obligation · TIA #04 DOOR REVISIONS ASI-02 CONTRACT FOR UEPH PHASE 1 REFERENCE NO. R00008 · W912DR23C0017
Modification A00007 · Feb 3, 2025 · $78,185 action obligation · CONTRACT FOR UEPH BARRACKS REPLACEMENT PHASE 1. REFERENCE NO. R00007. CHANGES AC AG AI AN AO. CONTRACT AMOUNT INCREASED BY $78,184.68. NO SCHEDULE CHANGE. HARD COPY SIGNED BY ANDRES ALVAREZ, PROJECT EXECUTIVE AND BY CEDRIC V. BAZEMORE, USACE ACO · W912DR23C0017
Modification A00006 · Nov 4, 2024 · $13,290 action obligation · CHILLER UNIT PER RFI#0007 CONTRACT FOR UEPH PHASE 1. REFERENCE NO. R00006 AA CHILLER UNIT PER RFI#0007 SEE PAGE 2. · W912DR23C0017
Modification A00005 · Sep 19, 2024 · $12,332 action obligation · REPLACE MATERIALS IN ACCORDANCE WITH BAA CONTRACT FOR UEPH PHASE 1. REFERENCE NO. R00005 AT REPLACE MATERIALS IN ACCORDANCE WITH BAA SEE PAGE 2. · W912DR23C0017
Modification A00004 · Aug 7, 2024 · $333,081 action obligation · CONTRACTOR SHALL BE COMPENSATED FOR THE DIFFERENCE BETWEEN THE BID RFP WAGE DETERMINATION (MD20220039 DATED 10/07/2022) AND THE AWARD WAGE DETERMINATION (MD20230039, DATED 06/02/2023). · W912DR23C0017
Modification A00003 · Jul 12, 2024 · $1,105 action obligation · UNFORESEEN CONCRETE PAD PER RFI-037 CONTRACT FOR UEPH PHASE 1. REFERENCE NO. R00003 AB UNFORESEEN CONCRETE PAD PER RFI-037 · W912DR23C0017
Modification A00002 · May 23, 2024 · $31,831 action obligation · CONT FOR UEPH BARRACKS REPLACEMENT PHASE 1. REF NO. R00002. AF-1 REMOVE AND REP SMH-1. CONT AMT INCREASED BY $31,830.56. NO SCHED CHANGE. RMS HARD COPY WAS SIGNED BY ANDRES ALVAREZ, PROJ EXEC ON 6 MAY 2024 AND ACCEPTED BY C. BAZEMORE, USACE ACO. · W912DR23C0017
Modification A00001 · Apr 17, 2024 · $0 action obligation · CONTRACT FOR UEPH BARRACKS REPLACEMENT PHASE 1. REFERENCE NO. R00001. AD WEATHER TIME EXT JAN 24 TO JAN 24. NO CONTRACT AMOUNT INCREASE. PERFORMANCE PD EXTENDED BY 7 DAYS. RMS HARD COPY FOR THIS UNILATERAL ACTION WAS SIGNED BY C. BAZEMORE, USACE ACO. · W912DR23C0017
Modification P00001 · Aug 15, 2023 · $0 action obligation · NOTICE TO PROCEED, UEPH BARRACKS REPLACEMENT, FT. MEADE, MD · W912DR23C0017
Modification 0 · Jun 9, 2023 · $83,789,463 action obligation · UNACCOMPANIED ENLISTED PERSONNEL HOUSING (UEPH) BARRACKS REPLACEMENT, FORT. MEADE, MARYLAND · W912DR23C0017