- Award ID
- W912DW25C0007
- Contractor
- JR MERIT, INC.
- Sub-agency / office
- Department of the Army
- Funding agency
- Corps of Engineers - Civil Works
- Award amount
- $8,863,737
- Period of performance
- Feb 15, 2025 – Aug 1, 2027
- NAICS
- 237990 — Other Heavy and Civil Engineering Construction
- Place of performance
- BRIDGEPORT, WA, 988130131, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 2 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $9,333,598 · Obligated $8,604,896 · Potential value $9,333,598 · Latest action obligation $94,169
CABLE AND CONDUIT SCHEDULE REVISIONS CONTRACT FOR CJD POWERHOUSE SUMP PUMP CONTROLS AT BRIDGEPORT, WAREFERENCE NO. R00004THIS IS A MODIFICATION TO W912DW25C0007A00005 TO OBLIGATE FUNDING TO CLIN 1003.
Most recent · Modification A00009 · Jun 16, 2026 · $94,169 action obligation · CABLE AND CONDUIT SCHEDULE REVISIONS CONTRACT FOR CJD POWERHOUSE SUMP PUMP CONTROLS AT BRIDGEPORT, WAREFERENCE NO. R00004THIS IS A MODIFICATION TO W912DW25C0007A00005 TO OBLIGATE FUNDING TO CLIN 1003. · W912DW25C0007
Modification A00008 · Jun 3, 2026 · $114,930 action obligation · CABLE AND CONDUIT SCHEDULE REVISIONS CONTRACT FOR CJD POWERHOUSE SUMP PUMP CONTROLS AT BRIDGEPORT, WAREFERENCE NO. R00004THIS IS A MODIFICATION TO W912DW25C0007A00005 TO OBLIGATE FUNDING TO CLIN 1003. · W912DW25C0007
Modification A00007 · Mar 10, 2026 · $50,000 action obligation · CABLE AND CONDUIT SCHEDULE REVISIONS CONTRACT FOR CJD POWERHOUSE SUMP PUMP CONTROLS AT BRIDGEPORT, WAREFERENCE NO. R00004THIS IS A MODIFICATION TO W912DW25C0007A00005 TO OBLIGATE FUNDING TO CLIN 1003. · W912DW25C0007
Modification A00006 · Jan 28, 2026 · $127,862 action obligation · CABLE AND CONDUIT SCHEDULE REVISIONS CONTRACT FOR CJD POWERHOUSE SUMP PUMP CONTROLS AT BRIDGEPORT, WAREFERENCE NO. R00004THIS IS A MODIFICATION TO W912DW25C0007A00005 TO OBLIGATE FUNDING TO CLIN 1003. · W912DW25C0007
Modification A00005 · Jan 15, 2026 · $0 action obligation · CABLE AND CONDUIT SCHEDULE REVISIONS CONTRACT FOR CJD POWERHOUSE SUMP PUMP CONTROLS AT BRIDGEPORT, WAREFERENCE NO. R00004 · W912DW25C0007
Modification P00003 · Nov 12, 2025 · $4,885,695 action obligation · CJD POWERHOUSE SUMP PUMPS AND CONTROLS · W912DW25C0007
Modification A00001 · Oct 16, 2025 · $99,041 action obligation · SP002 REMOVE GFE FROM PLC EQUIPMENT CONTRACT FOR CJD POWERHOUSE SUMP PUMP & CONTROLS AT BRIDGEPORT, WA REFERENCE NO. R00002 · W912DW25C0007
Modification P00002 · Sep 25, 2025 · $591,524 action obligation · SP001 REPLACE CQ01 CONTRACT FOR CJD POWERHOUSE SUMP PUMP & CONTROLS AT BRIDGEPORT, WA REFERENCE NO. R00001 · W912DW25C0007
Modification P00001 · Jun 9, 2025 · $0 action obligation · INSTALL PUMPS AND PIPING · W912DW25C0007
Modification 0 · Jan 29, 2025 · $2,558,775 action obligation · CJD PH SUMP PUMPS AND CONTROLS UPGRADE · W912DW25C0007