- Award ID
- W912EQ24C0010
- Contractor
- C. J. MAHAN CONSTRUCTION COMPANY, LLC
- Sub-agency / office
- Department of the Army
- Funding agency
- Corps of Engineers - Civil Works
- Award amount
- $23,331,284
- Period of performance
- Jun 21, 2024 – Jul 17, 2026
- NAICS
- 237110 — Water and Sewer Line and Related Structures Construction
- Place of performance
- BISCOE, AR, 720170190, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 1 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $26,930,869 · Obligated $26,930,869 · Potential value $26,930,869 · Latest action obligation $100,484 · Outlays $1,273,393
Most recent · Modification A00014 · Jun 30, 2026 · $100,484 action obligation · THIS SOLICITATION IS FOR THE RE-PROCUREMENT OF CONSTRUCTION SERVICES. WORK CONSISTS OF CONSTRUCTION OF THE (BASE BID) PUMP STATION SUPERSTRUCTURE ABOVE ELEVATION 190.0. · W912EQ24C0010
Modification A00013 · May 28, 2026 · $193,881 action obligation · THIS SOLICITATION IS FOR THE RE-PROCUREMENT OF CONSTRUCTION SERVICES. WORK CONSISTS OF CONSTRUCTION OF THE (BASE BID) PUMP STATION SUPERSTRUCTURE ABOVE ELEVATION 190.0. · W912EQ24C0010
Modification A00012 · May 20, 2026 · $13,050 action obligation · THIS SOLICITATION IS FOR THE RE-PROCUREMENT OF CONSTRUCTION SERVICES. WORK CONSISTS OF CONSTRUCTION OF THE (BASE BID) PUMP STATION SUPERSTRUCTURE ABOVE ELEVATION 190.0. · W912EQ24C0010
Modification A00011 · Apr 13, 2026 · $15,128 action obligation · THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, AND MATERIALS AND ANY INCIDENTAL WORK REQUIRED TO PERFORM HIGH RESOLUTION SCANS OF THE FOUR 84IN DISCHARGE PIPES TO DETERMINE THE CURRENT AS-BUILT CONDITIONS AND PROVIDE A REPORT OF FINDINGS. · W912EQ24C0010
Modification A00010 · Mar 23, 2026 · $125,620 action obligation · THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, AND MATERIALS AND ANY INCIDENTAL WORK REQUIRED TO PERFORM HIGH RESOLUTION SCANS OF THE FOUR 84IN DISCHARGE PIPES TO DETERMINE THE CURRENT AS-BUILT CONDITIONS AND PROVIDE A REPORT OF FINDINGS. · W912EQ24C0010
Modification P00005 · Mar 4, 2026 · $1,208,688 action obligation · THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, AND MATERIALS AND ANY INCIDENTAL WORK REQUIRED TO PERFORM HIGH RESOLUTION SCANS OF THE FOUR 84IN DISCHARGE PIPES TO DETERMINE THE CURRENT AS-BUILT CONDITIONS AND PROVIDE A REPORT OF FINDINGS. · W912EQ24C0010
Modification A00009 · Jan 30, 2026 · $12,941 action obligation · THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, AND MATERIALS AND ANY INCIDENTAL WORK REQUIRED TO PERFORM HIGH RESOLUTION SCANS OF THE FOUR 84IN DISCHARGE PIPES TO DETERMINE THE CURRENT AS-BUILT CONDITIONS AND PROVIDE A REPORT OF FINDINGS. · W912EQ24C0010
Modification A00008 · Dec 4, 2025 · $88,808 action obligation · CMU BOND BEAM VOIDS CONTRACT FOR GRAND PRAIRIE PUMP STATION REPROCUREMENT AT DEVALLS BLUFF, AR REFERENCE NO. R00011 · W912EQ24C0010
Modification A00007 · Nov 18, 2025 · $112,500 action obligation · PCV CABINET, BATHROOM FLOOR, BUSHING BOX CONTRACT FOR GRAND PRAIRIE PUMP STATION REPROCUREMENT AT DEVALLS BLUFF, AR REFERENCE NO. R00010 · W912EQ24C0010
Modification P00004 · Oct 22, 2025 · $1,208,114 action obligation · ELECTRICAL RFIS AND MOTOR SYNC CONTRACT FOR GRAND PRAIRIE PUMP STATION REPROCUREMENT AT DEVALLS BLUFF, AR REFERENCE NO. R00009 · W912EQ24C0010
Modification A00006 · Sep 26, 2025 · $172,474 action obligation · GROUNDING DEFICIENCIES CONTRACT FOR GRAND PRAIRIE PUMP STATION REPROCUREMENT AT DEVALLS BLUFF, AR REFERENCE NO. R00008 · W912EQ24C0010
Modification A00005 · Sep 24, 2025 · $60,000 action obligation · PROCUREMENT OF CHILLERS FOR MOTOR COOLING SYSTEM. · W912EQ24C0010
Modification A00004 · Aug 7, 2025 · $452,287 action obligation · MV SWGR, MV MCC, CONDUIT, BUSHING BOX, FLOWMETER CONTRACT FOR GRAND PRAIRIE PUMP STATION REPROCUREMENT AT DEVALLS BLUFF, AR REFERENCE NO. R00006 · W912EQ24C0010
Modification A00003 · Jul 23, 2025 · $233,964 action obligation · DISCHARGE PIPE FLANGE MACHINING · W912EQ24C0010
Modification P00003 · Jun 26, 2025 · $1,057,962 action obligation · GRAND PUMP STATION REPROCUREMENT MODIFICATION FOR ELEVATOR · W912EQ24C0010
Modification P00002 · Jun 20, 2025 · $1,288,320 action obligation · GRAND PRAIRIE PUMPING STATION RE-PROCUREMENT · W912EQ24C0010
Modification A00002 · May 30, 2025 · $30,277 action obligation · STOP LOG AND LIFTING BEAM STORAGE RACK CONTRACT FOR GRAND PRAIRIE PUMP STATION REPROCUREMENT AT DEVALLS BLUFF, AR REFERENCE NO. R00003 · W912EQ24C0010
Modification A00001 · Mar 12, 2025 · $5,659 action obligation · GRATING SHIMS AT N VALVE ACCESS CONTRACT FOR GRAND PRAIRIE PUMP STATION REPROCUREMENT AT DEVALLS BLUFF, AR REFERENCE NO. R00001 · W912EQ24C0010
Modification P00001 · Sep 20, 2024 · $0 action obligation · GRAND PRAIRIE PUMPING STATION RE-PROCUREMENT · W912EQ24C0010
Modification 0 · Jun 21, 2024 · $18,620,920 action obligation · GRAND PRAIRIE PUMP STATION RE-PROCUREMENT · W912EQ24C0010