- Award ID
- W912ER18C0004
- Contractor
- MIDMAC CONTRACTING COMPANY W.L.L
- Sub-agency / office
- Department of the Army
- Award amount
- $312,657,562
- Period of performance
- Nov 16, 2017 – Apr 30, 2026
- NAICS
- 236220 — Commercial and Institutional Building Construction
- Place of performance
- QAT
- Competition
- NOT AVAILABLE FOR COMPETITION · Set-aside: NO SET ASIDE USED. · 3 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $312,658,121 · Obligated $312,012,880 · Potential value $313,868,072 · Latest action obligation $559 · Outlays $549,853
Most recent · Modification A00007 · Jul 1, 2026 · $559 action obligation · DESCOPE HYDRANT AND ACS ADD A AT EG BLD · W912ER18C0004
Modification A00006 · May 8, 2026 · $0 action obligation · EPIC FURY TIME EXTENSION · W912ER18C0004
Modification P00026 · Sep 22, 2025 · $1,891,445 action obligation · SITE CIVIL WORK. CONSTRUCT EIGHT ADA MISSILE LAUNCH PADS · W912ER18C0004
Modification A00005 · Sep 7, 2025 · $0 action obligation · QF004 WEATHER TIME EXTENSION FEB 25 AND JUL 25 · W912ER18C0004
Modification A00004 · Jul 8, 2025 · $29,206 action obligation · CR0059 SITE 1 AND 4A MISCELLANEOUS CHANGES · W912ER18C0004
Modification A00003 · May 19, 2025 · $0 action obligation · CHANGE CONTRACT COMPLETION DATE (CCD) · W912ER18C0004
Modification A00002 · Mar 3, 2025 · $-256,971 action obligation · A0002-QA0056 DESCOPE CHAIN-LINK FENCE SITE 4A · W912ER18C0004
Modification P00025 · Jun 5, 2024 · $21,830,644 action obligation · ADDITIONAL BUILDINGS AND SITE WORK ADDED. · W912ER18C0004
Modification P00024 · Feb 15, 2024 · $0 action obligation · ROLLING 2019 FUNDING THAT WILL EXPIRE/CANCEL TO ANOTHER NEW CLIN · W912ER18C0004
Modification P00023 · Nov 16, 2023 · $22,289,790 action obligation · QF001 REA SETTLEMENT PROLONGATION COSTS FOR REA, SHIELD 5 SITE 1 AND 4A, QATAR · W912ER18C0004
Modification P00022 · Jul 12, 2023 · $0 action obligation · MODIFICATION IS ISSUED TO ROLL OVER FY14 FUNDING TO NEW FY 19 FUNDING. · W912ER18C0004
Modification P00021 · Apr 4, 2023 · $2,379,970 action obligation · 1. THE PURPOSE OF THIS MODIFICATION TO RECORD THE PAYMENT OF A REQUEST FOR EQUITABLE ADJUSTMENT (REA) AND ADD NEW CLIN 0425 REA SITE CIVIL EARTHWORKS ON CONTRACT W912ER-18-C-0004, SHIELD 5 SITE 1 &4. · W912ER18C0004
Modification A00001 · Feb 2, 2023 · $69,909 action obligation · A00001 CLIMATE CONTROL & PAVILION LADDER - ADDITIONAL COSTS INCURRED FOR TEMPERATURE CONTROLLED STORAGE AND ADDITIONAL COSTS INCURRED DUE TO INSTALLATION OF LADDER TO ACCESS HVAC EQUIPMENT ON PAVILION ROOF. · W912ER18C0004
Modification P00020 · Jun 24, 2022 · $2,023,783 action obligation · MODIFICATION P00020 IS ISSUED FOR THE NEGOTIATED AGREEMENT OF RFP-0025 CONTINUATION (SITE 4A RECONFIGURATION), RFP-0037 (MV WORKS), RFP-0038 (WATER & SEWAGE REMOVAL), AND RFP-0039 (SITE 4A LAYOUT & S1 ACCESS DOOR FOR FACILITY 402). · W912ER18C0004
Modification P00019 · Apr 12, 2021 · $3,176,472 action obligation · MODIFICATION P00019 IS ISSUED FOR THE NEGOTIATED AGREEMENT OF RFP-0025 (SITE 4A RECONFIGURATION) AND RFP-0036 (SITE 1, ACCESS DOOR BETWEEN ROOMS BE136A AND BE137A IN FACILITY 402). · W912ER18C0004
Modification P00018 · Nov 18, 2020 · $7,177 action obligation · MODIFICATION P00018 IS ISSUED TO ADD TWO (2) SELF-LATCHING METAL DOORS AT THE RAMPS LEADING TO THE SWIMMING POOL LOCATED AT FACILITY 309, OFFICERS CLUB, ON SITE 1. · W912ER18C0004
Modification P00017 · Oct 30, 2020 · $4,117,585 action obligation · MODIFICATION P00017 IS ISSUED FOR THE NEGOTIATED AGREEMENT OF THE FOLLOWING CHANGES ON SITE 1: RFP-0022 (PDS) RFP-0028 (FOOTBALL PITCH) RFP-0030 (UTILITY EXTENSION) RFP-0032 (FACILITY 503 VRF TO DX) AND RFP-0034 (BATCH 3) INCLUDING THE POLISHING OF THE GRANITE IN FACILITY 402 ENTRYWAY AND SUPPLYING AND INSTALLING FOUR (4) ACCESS CONTROL WORKSTATIONS WITH SPEED GATE SWITCHES FOR SPEED GATE MONITORING AT FACILITY 402 (THREE WORKSTATIONS) AND 406 (ONE WORKSTATION). · W912ER18C0004
Modification P00016 · Oct 30, 2020 · $1,096,245 action obligation · MISCELLANEOUS CHANGES ISSUED FOR THE NEGOTIATED AGREEMENT OF THE FOLLOWING CHANGES ON SITES 1 AND 4A: RFP-0021 (COP #14) RFP-0031 (NETWORK SWITCHES) RFP-0033 (ARMORED GUARD SHACKS) AND THE ADDITION OF THE PROTECTIVE COVERS FOR THE EMERGENCY POWER OFF (EPO) IN FACILITY 406 · W912ER18C0004
Modification P00015 · May 7, 2020 · $8,400,671 action obligation · MODIFICATION P00015 IS ISSUED FOR THE NEGOTIATED AGREEMENT OF THE FOLLOWING CHANGES ON SITES 1 AND 4A: RFP-0014 (PROVIDE FLOOR FINISH CHANGES IN VARIOUS FACILITIES AND WALL CHANGES IN FACILITY 401) RFP-0016 (FF&E) RFP-0017 (COP #12) RFP-0018 (COP #11) RFP-0019 (SITE 1 ACCESS) RFP-0020 (MISCELLANEOUS CIVIL WORKS ON SITE 4A) RFP-0023 (QESC REQUIRED CHANGES TO FACILITY 311) RFP-0024 (REF RELAY TO FACILITY 212 SUBSTATIONS) REF-0026 (LED VIDEO WALL IN FACILITY 402) RFP-0027 (SEVEN ADDITIONAL TELECOMM · W912ER18C0004
Modification P00014 · Dec 30, 2019 · $5,023,960 action obligation · MODIFICATION P00014 IS TO ADD THE REQUIREMENT FOR A DESIGN/BUILD OF A MOSQUE, PARADE GROUND AND A PAVILION ON SITE 1. · W912ER18C0004
Modification P00013 · Dec 1, 2019 · $625,556 action obligation · MODIFICATION P00013 IS TO INCORPORATE THE CHANGES OF COP #10. · W912ER18C0004
Modification P00012 · Jun 28, 2019 · $221,191 action obligation · MODIFICATION P00012 IS TO REVISE THE AUDITORIUM SEATS IN FACILITY 402, ADMINISTRATION BUILDING (LARGE) ON SITE 1. · W912ER18C0004
Modification P00011 · May 12, 2019 · $41,839 action obligation · MODIFICATION P00011 IS TO REVISE THE ELEVATOR IN FACILITY 406, C2 MAIN BUILDING (ADOC), FROM A ONE TON ELEVATOR TO A TWO TON ELEVATOR ON SITE 1. · W912ER18C0004
Modification P00010 · Mar 26, 2019 · $9,040 action obligation · MODIFICATION P00010 IS FOR ADDITIONAL 3D RENDERINGS AS IDENTIFIED IN THE MODIFICATION SCOPE OF WORK. · W912ER18C0004
Modification P00009 · Mar 25, 2019 · $151,099 action obligation · MODIFICATION P00009 IS FOR COSTS ASSOCIATED WITH PUBLIC WORKS AUTHORITY (ASHGHAL) TIE-IN AND ROADWAY TO THE ORBITAL HIGHWAY FROM SITE 1. · W912ER18C0004