- Award ID
- W912ES22C0003
- Contractor
- AMES CONSTRUCTION, INC.
- Sub-agency / office
- Department of the Army
- Funding agency
- Corps of Engineers - Civil Works
- Award amount
- $117,556,153
- Period of performance
- May 15, 2022 – Apr 29, 2027
- NAICS
- 237990 — Other Heavy and Civil Engineering Construction
- Place of performance
- FARGO, ND, 581047294, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 1 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $118,791,918 · Obligated $118,791,918 · Potential value $118,791,918 · Latest action obligation $162,821 · Outlays $19,707,759
Most recent · Modification A00014 · Jul 2, 2026 · $162,821 action obligation · (R-026) COMPENSATE THE CONTRACTOR FOR (REA-005) THE NECESSITY TO BUILD AN ACCESS ROAD TO THE RED RIVER STRUCTURE SITE FOLLOWING THE 3RD STREET CLOSURE; (REA-006) COMPENSATE THE CONTRACTOR FOR SEALING CRACKS IN THE CONTROL STRUCTURE. · W912ES22C0003
Modification A00013 · Jun 12, 2026 · $25,744 action obligation · (R-026) COMPENSATE THE CONTRACTOR FOR (REA-005) THE NECESSITY TO BUILD AN ACCESS ROAD TO THE RED RIVER STRUCTURE SITE FOLLOWING THE 3RD STREET CLOSURE; (REA-006) COMPENSATE THE CONTRACTOR FOR SEALING CRACKS IN THE CONTROL STRUCTURE. · W912ES22C0003
Modification A00012 · Jun 4, 2026 · $0 action obligation · CHANGE THE PROTECTIVE BOLLARD ALONG THE NORTH SIDE OF THE DAM WALLS, RATIO OF NUCLEAR DENSITY AND SAND CONE TESTS, BERM FILL LIFT, COMPACTION AND MOISTURE CONTENT REQUIREMENTS, MAXIMUM MOISTURE CONTROL LIMITS, AND DELETE PORTIONS OF SPECIFICATIONS. · W912ES22C0003
Modification A00011 · Apr 29, 2026 · $431,962 action obligation · (R-025 AND 027) ADJUST THE ESTIMATED CONTRACT QUANTITIES TO ACTUAL FINAL QUANTITIES FOR CLIN 0036AB STEEL H-PILE (HP 14X73), 0037AB STEEL H-PILE (HP 14X102), AND CLIN 0038AB SHEET PILE. · W912ES22C0003
Modification A00010 · Apr 10, 2026 · $0 action obligation · THIS CONTRACT IS MODIFIED TO: (R-017) EXTEND THE CONTRACT COMPLETION DATE BY 40 CALENDAR DAYS TO ACCOUNT FOR ADVERSE WEATHER BETWEEN AUGUST 2024 THROUGH DECEMBER 2025 · W912ES22C0003
Modification A00009 · Sep 18, 2025 · $29,296 action obligation · REVISE THE SUBMERGENCE RATIO EQUATION AND EQUATION 2 TO CORRECT IDENTIFIED ERRORS AND UPDATE ASSOCIATED SCREENS IDENTIFIES STAIN FOR THE CONCRETE TRUNNION GIRDERS AND ADDS A NEW PLAN SHEET DETAILING PROPER MOUNTING FOR THE OBJECT MARKER ASSEMBLIES. · W912ES22C0003
Modification A00008 · Jun 9, 2025 · $186,003 action obligation · REPLACES THE EXISTING SQUARE ALUMINUM LIGHT POLES, REPLACE THE COMMUNICATION CABLE, RUN 1.5-INCH CONDUIT TO THE MECHANICAL SERVICE BRIDGE, ADD LOW FLOW RADAR GAUGE, AND PROCURE AND INSTALL WIND SENSOR TOWER AND FOUNDATION FOR THE TOWER. · W912ES22C0003
Modification P00002 · Dec 11, 2024 · $442,935 action obligation · CHANGES TO TURF REINFORCEMENT MAT AND J-BULB SIZING · W912ES22C0003
Modification A00007 · Nov 15, 2024 · $0 action obligation · (R-17) EXTEND THE CONTRACT COMPLETION DATE BY 42 CALENDAR DAYS TO ACCOUNT FOR UNUSUALLY SEVERE WEATHER EXPERIENCED AT THE RED RIVER STRUCTURE PROJECT SITE BETWEEN THE MONTHS MARCH 2022 THROUGH JULY 2024. · W912ES22C0003
Modification P00001 · Oct 29, 2024 · $1,063,795 action obligation · INCLUDE RADIOGRAPHIC TESTING FOR ALL DIAGONAL CONNECTIONS IN SKIN PLATE BRACINGS AS IDENTIFIED IN DRAWINGS SG203 AND SG506. TO MITIGATE THE SCHEDULE IMPACTS- THE FINAL GATE WILL BE CONSTRUCTED DURING THE WINTER MONTHS INSIDE A HEATED ENCLOSURE. · W912ES22C0003
Modification A00006 · Sep 24, 2024 · $136,533 action obligation · REQUIRE THE CONTRACTOR TO RELOCATE THE TEMPORARY CONSTRUCTION FACILITIES FROM THEIR CURRENT LOCATION AT THE RED RIVER STRUCTURE SITE, TO INCLUDE MOVING JOB TRAILERS, REMOVING AND RELOCATING THE ACCESS ROAD AND CONSTRUCTING A NEW LAYDOWN PAD. · W912ES22C0003
Modification A00005 · Aug 15, 2024 · $182,509 action obligation · 1. (R-0012) REVISE THE PIER AND ABUTMENT STAIRS AND INSTALL ACCORDANCE WITH THE REVISED DESIGN CHANGE THE IMPERVIOUS FILL LIFT THICKNESS TO 9 INCHES. 2. (R0015) CHANGE THE WIDTH (EAST-WEST DIRECTION) OF THE (6) DOGGING PLATFORMS. · W912ES22C0003
Modification A00004 · Jul 22, 2024 · $307,153 action obligation · CHANGE THE SPECIFIED MACHINERY HOISTING EQUIPMENT FROM A WORM GEAR REDUCER TO A HELICAL GEAR AND CONDUCT COMPLIANCE VERIFICATION THROUGH LOAD TESTING BEFORE SHIPPING. THIS MODIFICATION INCLUDES MACHINERY GUARDS ON ALL EXPOSED ROTATING EQUIPMENT. · W912ES22C0003
Modification A00003 · Jun 27, 2024 · $116,173 action obligation · THE CHANGE ENCOMPASSES DESIGN CHANGES TO THE BRIDGES AND MECHANICAL PLATFORMS SCHEDULE CHANGES TO ALLOW EARLIER PLACEMENT OF EMBANKMENT AND FASTER REVIEWS OF FRACTURE CRITICAL WELDS AND CHANGES TO THE H-PILE TENSION CAPACITY. · W912ES22C0003
Modification A00002 · Jan 4, 2024 · $168,646 action obligation · (1) (R-02) REBAR SIZE CHANGE AND GATE SEAL HEATER (2) (R-04) REVISE TRUNNION GIRDER TRANSVERSE BARS (3) (R-06) COMPENSATE CONTRACTOR FOR REMOVAL OF HOUSE FOUNDATION (4) (R-10) PROVIDE A CREDIT TO THE GOVERNMENT FOR REPLACING THE CQC MANAGER. · W912ES22C0003
Modification A00001 · Dec 7, 2022 · $25,996 action obligation · THIS CONTRACT IS MODIFIED TO: PROVIDE 6 LICENSES TO ACCESS THE CONTRACTOR'S CONSTRUCTION MANAGEMENT SOFTWARE AND 6 TABLETS SIMILAR IN SIZE AND CAPABILITIES TO THOSE USED BY AMES CONSTRUCTION PROJECT SITE MANAGEMENT. · W912ES22C0003
Modification 0 · Mar 15, 2022 · $114,897,115 action obligation · CONSTRUCTION OF THE RED RIVER STRUCTURE OF THE FARGO MOORHEAD METROPOLITAN AREA FLOOD RISK MANAGEMENT PROJECT · W912ES22C0003