- Award ID
- W912ES24C0011
- Contractor
- PWS INC
- Sub-agency / office
- Department of the Army
- Funding agency
- Corps of Engineers - Civil Works
- Award amount
- $24,139,139
- Period of performance
- May 30, 2024 – Sep 30, 2027
- NAICS
- 237990 — Other Heavy and Civil Engineering Construction
- Place of performance
- COMSTOCK, MN, 565250001, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 6 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $24,930,335 · Obligated $24,930,335 · Potential value $24,930,335 · Latest action obligation $224,329 · Outlays $2,925,350
(R-006) ADJUST THE CONTRACT QUANTITIES TO ACTUAL FINAL QUANTITIES FOR THE FOLLOWING CLIN 0008 REMOVAL OF ROAD SURFACING-180TH AVE S, CLIN 0018 AGGREGATE SURFACE - 180TH AVE S, CLIN 0020 AGGREGATE BASE - 180TH AVE S, AND (R-010) CLIN 0045 RIPRAP R45.
Most recent · Modification A00005 · Jul 2, 2026 · $224,329 action obligation · (R-006) ADJUST THE CONTRACT QUANTITIES TO ACTUAL FINAL QUANTITIES FOR THE FOLLOWING CLIN 0008 REMOVAL OF ROAD SURFACING-180TH AVE S, CLIN 0018 AGGREGATE SURFACE - 180TH AVE S, CLIN 0020 AGGREGATE BASE - 180TH AVE S, AND (R-010) CLIN 0045 RIPRAP R45. · W912ES24C0011
Modification P00005 · Jun 25, 2026 · $0 action obligation · (R-008) COMPENSATE THE CONTRACTOR FOR SEALING OF TWO (2) WELLS ON THE SE-4 PROJECT SITE WHICH HAD NOT BEEN IDENTIFIED PRIOR TO AWARD. · W912ES24C0011
Modification A00004 · May 14, 2026 · $9,289 action obligation · (R-008) COMPENSATE THE CONTRACTOR FOR SEALING OF TWO (2) WELLS ON THE SE-4 PROJECT SITE WHICH HAD NOT BEEN IDENTIFIED PRIOR TO AWARD. · W912ES24C0011
Modification A00003 · May 11, 2026 · $0 action obligation · THIS CONTRACT IS MODIFIED TO: CORRECT AN ERROR IN MODIFICATION NUMBERING. · W912ES24C0011
Modification P00004 · Apr 17, 2026 · $557,578 action obligation · (R-009) EXTEND THE CONTRACT COMPLETION DATE BY 15 CALENDAR DAYS TO ACCOUNT FOR ADVERSE WEATHER. (R-005) ADJUST THE CLASS 5 TO CLASS 13, TO INCLUDE ADDITIONAL TESTING REQUIREMENTS. · W912ES24C0011
Modification A00002 · Oct 3, 2025 · $-25,984 action obligation · (R-002) CHANGE THE SOUTHERN EMBANKMENT AND INSPECTION TRENCH STARTING STATION (AT THE NORTH END OF THE PROJECT) FROM 53+80.00 TO 60+00.13. · W912ES24C0011
Modification A00001 · Sep 12, 2025 · $201,358 action obligation · (R-004) REMOVE AGGREGATE SURFACE MATERIAL ON 180TH AVE S AND 3RD ST. S AND REPLACE WITH SUITABLE MATERIAL. CONDUCT TESTING FOR CLAY CONTENT AND PI TO MEET MNDOT SPECIFICATION 3138.2.D.5. PROOF ROLL AGGREGATE SURFACE TO COMPACTION. · W912ES24C0011
Modification P00003 · Aug 4, 2025 · $70,018 action obligation · R-001: ADJUST THE COMPACTION AND MOISTURE CONTROL REQUIREMENTS FOR THE ROAD EMBANKMENT PORTIONS OF SE-4. · W912ES24C0011
Modification P00002 · Apr 2, 2025 · $0 action obligation · FMM SE-4 CONSTRUCTION · W912ES24C0011
Modification P00001 · Jun 14, 2024 · $0 action obligation · FMM SE-4 CONSTRUCTION · W912ES24C0011
Modification 0 · May 28, 2024 · $23,893,747 action obligation · FMM SE-4 CONSTRUCTION · W912ES24C0011