- Award ID
- W912GB18C0040
- Contractor
- BUNDESAMT FÜR BAUWESEN UND RAUMORDNUNG
- Sub-agency / office
- Department of the Army
- Award amount
- $6,126,091
- Period of performance
- Sep 20, 2018 – Jun 20, 2025
- NAICS
- 238990 — All Other Specialty Trade Contractors
- PSC
- PSC Z2FB
- Place of performance
- DEU
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 2 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $6,183,427 · Obligated $5,517,336 · Potential value $6,183,427 · Latest action obligation $3,318
Most recent · Modification A00011 · Mar 12, 2026 · $3,318 action obligation · INSTALL A ROOF HATCH TO ACCESS FACILITY ROOF FROM INTERIOR ATTIC SPACE. THE ROOF HATCH SHALL BE H 16 OD; F90 CLASSIFICATION, CORNER FRAME 1000MM X 1000MM DIMENSION (1 EACH). · W912GB18C0040
Modification A00010 · Mar 4, 2026 · $54,017 action obligation · CR036 PROVIDE EXTERIOR DOORS W/REMOTE ACCESS CONTROL CAPABILITIES, PER THE REVISED DOOR SCHEDULE AND LOCKING PLAN. PROVIDE BASEMENT WITH FIRE-RATED CABLING. CR038 REPAIR/REPLACE EXISTING DETERIORATED FACILITY GROUNDING/LIGHTNING PROTECTION SYSTEM. · W912GB18C0040
Modification A00009 · Jan 20, 2026 · $149,791 action obligation · CR030 ADD CARPENTRY/ROOFING AREA II CR034 ADD GUTTER COMPONENTSCR037 SMOKE/HEAT EXHAUST SYSTEMINSTALL AN OPERABLE WINDOW SMOKE AND HEAT EXHAUST SYSTEM IN THE STAIRWELLQTY REDUCTIONS - LV SPEC SECTIONS 09.04; 09.05; AND 09.10 · W912GB18C0040
Modification P00010 · Sep 26, 2025 · $-29,114 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER, BLDG. 2222, VILSECK · W912GB18C0040
Modification A00008 · Sep 26, 2025 · $135,981 action obligation · CONTRACT FOR ABG4 AB3-18-0175 ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY. REFERENCE NO. R00011. TOTAL CONTRACT PRICE INCREASED BY 118,928.20 EU. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 279 CALENDAR DAYS BY REASON OF THIS MODIFICATION. · W912GB18C0040
Modification A00007 · Jun 13, 2025 · $5,379 action obligation · CONTRACT FOR ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY. REFERENCE NO. R00010, ABG5-21, ASBESTOS FLOOR MAT'L, AREA II. TOTAL CONTRACT PRICE INCREASED BY 4,829.19 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. · W912GB18C0040
Modification A00006 · Apr 29, 2025 · $218,687 action obligation · CONTRACT FOR ABG4 AB3-18-0175 ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY. REFERENCE NO. R00009. TOTAL CONTRACT PRICE INCREASED BY 192,296.45 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. · W912GB18C0040
Modification A00005 · Mar 7, 2025 · $126,266 action obligation · CONTRACT FOR ABG4 AB3-18-0175 ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY, REFERENCE NO. R00008. TOTAL CONTRACT PRICE IS INCREASED BY 113,361.17 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. CORRECTION TO A00004. · W912GB18C0040
Modification A00004 · Feb 25, 2025 · $364,050 action obligation · CONTRACT FOR ABG4 AB3-18-0175 ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY, REFERENCE NO. R00008. TOTAL CONTRACT PRICE IS INCREASED BY 319,493.81 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. · W912GB18C0040
Modification A00003 · Dec 17, 2024 · $66,726 action obligation · CONTRACT FOR ABG4 AB3-18-0175 ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY REFERENCE NO. R00007. TOTAL CONTRACT PRICE IS INCREASED BY 58,071.79 EU. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. · W912GB18C0040
Modification A00002 · Nov 20, 2024 · $139,471 action obligation · CONTRACT FOR ABG4 AB3-18-0175 ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY. REFERENCE NO. R00006 CR002 ABG5-02, ADDITIONAL DEMO/HAZMAT REMOVAL CR004 ABG5-04, 2ND FL DEMO, INCL SUSP CEILING CR010 ABG5-10, JOBSITE COSTS FOR TIME IMPACTS. CONTRACT AMOUNT IS INCREASED BY 124,984.83, CONTRACT DURATION IS INCREASED BY 182 CALENDAR DAYS. · W912GB18C0040
Modification A00001 · Aug 22, 2024 · $32,805 action obligation · CONTRACT FOR ABG4 AB3-18-0175 ABG4 RENOVATE YOUTH CENTER AT VILSECK, GERMANY. REFERENCE NO. R00005 CR001 ABG5-01, ADD ELECRICAL DEMO/RELOCATE FA. CONTRACT AMOUNT IS INCREASED BY 28,876.84, CONTRACT DURATION IS UNCHAGED. · W912GB18C0040
Modification P00009 · Sep 27, 2023 · $11,757 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER, BLDG. 2222, VILSECK · W912GB18C0040
Modification P00008 · Aug 15, 2023 · $18,263 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER, BLDG. 2222 VILSECK · W912GB18C0040
Modification P00007 · Jul 28, 2023 · $-29,610 action obligation · SOFA ABGX RENOVATE YOUTH CENTER, BLDG. 2222 · W912GB18C0040
Modification P00006 · Jul 14, 2022 · $2,649,132 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER, BLDG. 2222 VILSECK · W912GB18C0040
Modification P00005 · May 10, 2022 · $-2,182,995 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER, BLDG. 2222 VILSECK · W912GB18C0040
Modification P00004 · Sep 20, 2021 · $1,538,566 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER BLDG 2222 SOUTH CAMP VILSECK · W912GB18C0040
Modification P00003 · May 3, 2021 · $132,247 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER BLDG 222, VILSECK · W912GB18C0040
Modification P00002 · Sep 21, 2020 · $-76,262 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER, BLDG. 2222, VILSECK · W912GB18C0040
Modification P00001 · Apr 6, 2020 · $63,464 action obligation · SOFA ABG-X RENOVATE YOUTH CENTER, BLDG. 2222, VILSECK · W912GB18C0040
Modification 0 · Sep 29, 2018 · $2,275,187 action obligation · 18 CONST (K) WORK, 92635 RENOVATE YOUTH · W912GB18C0040