- Award ID
- W912QR20C0054
- Contractor
- A & K CONSTRUCTION INC
- Sub-agency / office
- Department of the Army
- Award amount
- $59,294,983
- Period of performance
- Sep 30, 2020 – Aug 2, 2024
- NAICS
- 236220 — Commercial and Institutional Building Construction
- PSC
- PSC Y1CA
- Place of performance
- FORT CAMPBELL, TN, 422233566, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 8 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $59,771,923 · Obligated $59,771,923 · Potential value $59,771,923 · Latest action obligation $17,000 · Outlays $1,739,720
Most recent · Modification A00082 · Jun 8, 2026 · $17,000 action obligation · A. SCOPE OF WORK THIS MODIFICATION EXTENDS THE TIME FOR PERFORMANCE ALLOWED UNDER SPECIFICATION SECTION 00 80 00.00 06 FOR DELAYS CAUSED BY ADVERSE WEATHER IN EXCESS OF ANTICIPATED DURING THE PERIOD 01 NOVEMBER 2024 THROUGH 31 JULY 2025. THE FOLLOW · W912QR20C0054
Modification A00080 · Nov 13, 2025 · $18,000 action obligation · CR 00066-2 MISC CHANGES PART 2 FINAL · W912QR20C0054
Modification A00081 · Nov 13, 2025 · $0 action obligation · CR 00067 WEATHER TIME EXTENSION NOV 24 - JUL 25 · W912QR20C0054
Modification A00079 · Oct 27, 2025 · $15,000 action obligation · CR 00065-2 RFI 486- PART 2 FINAL · W912QR20C0054
Modification A00078 · Aug 19, 2025 · $4,000 action obligation · CR 00068-2 RFI 491, BOLLARDS, WAINSCOT -PART II FINAL · W912QR20C0054
Modification A00077 · Jul 3, 2025 · $45,000 action obligation · PART I NTP BOLLARDS CASE 00068-1 · W912QR20C0054
Modification A00076 · Jul 2, 2025 · $20,500 action obligation · CR 00064-2 RFI 484, 485- PART 2 FINAL · W912QR20C0054
Modification A00075 · Jul 2, 2025 · $10,400 action obligation · CR 00063-2 RFI 447, 463, 479 - PART 2 · W912QR20C0054
Modification A00074 · Jun 30, 2025 · $2,000 action obligation · CR 00066-1 MISC CHANGES (PART 1)/ · W912QR20C0054
Modification A00073 · Jun 27, 2025 · $0 action obligation · CR 00041 MECHANICAL CHANGES PART 2 FINAL · W912QR20C0054
Modification A00071 · May 30, 2025 · $52,620 action obligation · CR0060-2 UNSUITABLE SOILS PART II FINAL A00071 · W912QR20C0054
Modification A00072 · May 30, 2025 · $3,000 action obligation · RFI 486 POWER FOR SMOKE DAMPERS · W912QR20C0054
Modification A00069 · May 14, 2025 · $17,275 action obligation · CR 00061-2 RFI 442,443 PT 2 FINAL · W912QR20C0054
Modification A00070 · May 14, 2025 · $13,749 action obligation · RFI 454, 457 - PART 2 FINAL · W912QR20C0054
Modification A00068 · May 7, 2025 · $31,396 action obligation · CR 00059-2 RFI 424, 429, 431 & 437 (PART 2 FINAL)/ · W912QR20C0054
Modification A00067 · May 6, 2025 · $32,000 action obligation · CR 00058 2 AV CABLING UPGRADE PART II FINAL · W912QR20C0054
Modification A00066 · May 2, 2025 · $35,000 action obligation · CR 00057-2 RFI: 413, 415 & 416 (PART 2 FINAL · W912QR20C0054
Modification A00065 · May 1, 2025 · $0 action obligation · CR 00056-2 MISC. CHANGES RFI 402 & 410 PT 2 FINAL / · W912QR20C0054
Modification A00064 · Apr 17, 2025 · $5,000 action obligation · CR 00064-1 RFI 484, 485-PART 1 NTP- · W912QR20C0054
Modification A00063 · Apr 9, 2025 · $15,000 action obligation · CR 00063-1 RFI 447, 463, 479 - PART 1 NTP · W912QR20C0054
Modification A00062 · Feb 28, 2025 · $5,000 action obligation · CR 00062-1 RFI 454, 457 PT 1 NTP · W912QR20C0054
Modification A00061 · Feb 27, 2025 · $23,000 action obligation · CR 00055-2 WAINSCOT TOP TRIM- RFI 300 PT 2 FINAL · W912QR20C0054
Modification A00060 · Feb 26, 2025 · $40,000 action obligation · PERFORMANCE CHGS & RFI 370-PART II FINAL · W912QR20C0054
Modification A00059 · Feb 20, 2025 · $18,500 action obligation · LP4 LIGHTING CONTROLS PT 2 FINAL/ · W912QR20C0054
Modification A00058 · Jan 31, 2025 · $5,000 action obligation · CR 0061-1 RFI 442,443 PT I NTP INSTALL CAST DOWN SPOUT AND GUTTER EXPOSED PIPING IN KITCHEN - FUR OUT WALL WITH METAL STUDS AND INSTALL STAINLESS STEEL WALL PANELS FTC MIDDLE SCHOOL · W912QR20C0054