- Award ID
- W912QR24C0006
- Contractor
- ZODIAC-POETTKER HBZ JOINT VENTURE III, LLC
- Sub-agency / office
- Department of the Army
- Award amount
- $20,111,426
- Period of performance
- Apr 11, 2024 – Dec 22, 2026
- NAICS
- 236220 — Commercial and Institutional Building Construction
- PSC
- PSC Y1CA
- Place of performance
- SCOTT AFB, IL, 622256140, USA
- Competition
- FULL AND OPEN COMPETITION · Set-aside: NO SET ASIDE USED. · 3 offers
- Pricing
- FIRM FIXED PRICE
- Financial breakdown
- Current value $21,037,518 · Obligated $21,037,518 · Potential value $22,268,518 · Latest action obligation $67,790
Most recent · Modification A00012 · Jun 24, 2026 · $67,790 action obligation · CHANGE REQUEST CR27 - DESIGN DELAY REA - WINTER MASONRY INCREASED: $67,789.95TIME EXTENSION: 7 DAYS CONTRACT REQUIRED COMPLETION DATE 31 MARCH 2027 · W912QR24C0006
Modification A00011 · Jun 11, 2026 · $248,235 action obligation · CHANGE REQUEST CR28 - REAL PROPERTY ITEMS CR30 - CCTV AND INTERCOM ADDITIONSINCREASED: $248,235.04TIME EXTENSION: 0 DAYS CONTRACT REQUIRED COMPLETION DATE 24 MARCH 2027 · W912QR24C0006
Modification A00010 · May 14, 2026 · $228,037 action obligation · CHANGE REQUEST CR18-2 TELECOMM OUTSIDE PLANT - INSTALL INCREASED: $228,037.43TIME EXTENSION: 0 DAYS CONTRACT REQUIRED COMPLETION DATE 24 MARCH 2027 · W912QR24C0006
Modification A00009 · May 1, 2026 · $199,188 action obligation · CHANGE REQUEST CHANGE ELEC. UTIL. - PART 2 INSTALL INCREASED: $199,187.75TIME EXTENSION: 0 DAYS CONTRACT REQUIRED COMPLETION DATE 24 MARCH 2027 · W912QR24C0006
Modification A00008 · Jan 27, 2026 · $81,666 action obligation · CHANGE REQUEST CR24 TITLE: DOAS SYSTEM CHANGE (RFI-47) INCREASED: $81,666.12TIME EXTENSION: 0 DAYS CONTRACT REQUIRED COMPLETION DATE 24 MARCH 2027 · W912QR24C0006
Modification A00007 · Jan 6, 2026 · $20,857 action obligation · CHANGE REQUEST CR26 DESIGN DELAY REA INCREASED $20,857.09TIME EXTENSION: 92 DAYS CONTRACT REQUIRED COMPLETION DATE 24 MARCH 2027 · W912QR24C0006
Modification A00006 · Sep 29, 2025 · $280,395 action obligation · CR12 UPDTD DOORS CR13 KITCHN DRAIN PPNG PVC SWAP CR14 ENTRY VESTBLE GLASS WALLS CR15 EVAC PAD RELOCAT CR16 PLAYGRND DESIGN PCKGE CR17 UPDTD CASEWORK DETAILS CR19 UPDTD WINDOW DETAILS CR21 CONTAMD SOIL BURIAL CR22 HVAC SPLIT SYST CR23 SEPTIC TANK RMVL · W912QR24C0006
Modification A00005 · Sep 22, 2025 · $243,907 action obligation · CR9-2 CHANGE ELECT UTIL. - EQUIPMENT · W912QR24C0006
Modification A00004 · Jun 23, 2025 · $75,000 action obligation · CR18 1 TELECOMM OUTSIDE PLANT PART 1 · W912QR24C0006
Modification A00003 · Jun 13, 2025 · $-280,000 action obligation · CHANGE REQUEST CR07 AMERICAN WATER DLA PAYMENT · W912QR24C0006
Modification P00002 · Jun 13, 2025 · $0 action obligation · EXECUTIVE ORDER MODIFICATION · W912QR24C0006
Modification A00002 · Apr 23, 2025 · $32,124 action obligation · CR 002 DELETE STORM SHELTER CR 003 DELETE ACS CR 004 DELETE CATV CR 005 CHANGE SAN SEWER CR 008 REDUCE COMMUNICATIONS OUTSIDE PLANT CR 010 DAYLIGHT HARVESTING CONSTRUCTION OF SAFB CDC · W912QR24C0006
Modification A00001 · Dec 6, 2024 · $50,000 action obligation · CR 009-1 PART 1 - CHANGE ELECTRIC UTILITY (NTP) BASE - CONSTRUCTION OF SAFB CDC · W912QR24C0006
Modification P00001 · May 2, 2024 · $0 action obligation · ISSUANCE OF NOTICE TO PROCEED (NTP) - CONSTRUCTION OF SAFB CDC · W912QR24C0006
Modification 0 · Apr 11, 2024 · $19,710,000 action obligation · DESIGN BUILD CONSTRUCTION OF A CHILD DEVELOPMENT CENTER AT SCOTT AIR FORCE BASE, IL · W912QR24C0006